One of our clients in the Permian Basin needed to reduce their wellbore construction costs in order to achieve their drilling budget.

They had a multi-rig drilling campaign using full-size rigs, which had a high equipment day rate and labor costs. We worked with the client to determine that for the majority of their program, they would need 17-1/2” surface hole drilled to depths ranging between 1,100 and 1,650 feet, and then 13-3/8” casing run and cemented.

Based on these characteristics, EnerCorp implemented a solution for the client that typically saved them between 35% and 40% on drilling their surface interval.